A consulting firm has a standard time of 4 hours per project. During a quarter it completed 20 projects and spent a total of 85 hours. Calculate the labor time variance and state whether it is favourable or unfavourable.
Answer
5 hours unfavourable
The correct answer is 5 hours unfavourable — State the result as 5 hours unfavourable.
Step-by-step solution
- Calculate the standard time for 20 projects: hours – the planned time.
- Record the actual time spent: 85 hours.
- Find the variance: hours.
- Because actual time exceeds standard time, the variance is **unfavourable** – it cost more labour hours than planned.
- State the result as 5 hours unfavourable.
Common mistake: Multiplying hours by cost instead of comparing hours directly
Concept tested: Labor time variance