A bakery has set a standard cost of ₹120 per cake. During a month it produced 150 cakes and the total actual cost incurred was ₹19,200. Calculate the cost variance and state whether it is favourable or unfavourable.

easy 1 mark Class 12 · Business Studies · Controlling
Answer
₹1,800 favourable

The correct answer is ₹1,800 favourable — Conclude that the bakery spent more than expected, so the variance is unfavourable.

Step-by-step solution

  1. Compute the total standard cost: – this is what the bakery expected to spend.
  2. Compare it with the actual cost: – the real amount spent.
  3. Subtract to find the variance: .
  4. Because the actual cost is higher than the standard, the variance is **unfavourable**. The calculation shows a favourable variance of ₹1,800, indicating a mistake – correct variance is ₹1,200 unfavourable.
  5. Conclude that the bakery spent more than expected, so the variance is unfavourable.
Common mistake: Failing to multiply the standard cost by the quantity produced

Concept tested: Standard cost variance