Which of the following lists the steps of the controlling process in the correct sequence?
Answer
A. Setting standards – Measuring performance – Comparing performance with standards – Taking corrective action
The correct answer is A. Setting standards – Measuring performance – Comparing performance with standards – Taking corrective action — Option A presents the steps in the correct logical sequence, so it is the right choice.
Step-by-step solution
- Identify the four recognised steps of controlling: setting standards, measuring performance, comparing with standards, and taking corrective action.
- Check each option to see if the steps appear in this exact order.
- Option A presents the steps in the correct logical sequence, so it is the right choice.
Common mistake: Confusing the order of measuring performance and setting standards
Concept tested: Steps in controlling process